Hotel Bonus Inn: 210 rooms renovated on a one-day takt

Hotel renovationConstiFinland

Consti renovated the 210 rooms of Hotel Bonus Inn on a one-day takt time, with the goal of keeping disruption to the running hotel to a minimum. 100 takts covered 400 takt areas and 9,000 tasks in Mestamaster over 7 months. The project finished on schedule and under budget, and Consti named it worksite of the year.

The Bonus Inn project was perfect for takt production given the clear repeatability of the work. The technicians and sub-contractors were also exceptionally well integrated into the project. With such a clear repeatability, the traditional production methods could not have achieved the same results in terms of quality or economy.

Juha Haltia

Project manager, Consti

Consti

1st

place

Recognised as Consti's worksite of the year

7M€

Project total value

210 hotel rooms in seven months.

7

months duration

On schedule and under budget.

100

Takts

On a one-day takt.

400

Takt areas

210 hotel rooms.

9,000

Tasks in Mestamaster

Across 400 takt areas, on a one-day takt.

The Customer

Consti is one of the biggest players in the Finnish renovation industry, with a yearly revenue of €300M. Consti named Bonus Inn its worksite of the year, judged on financials, customer satisfaction and quality.

What was done

A full renovation of a 210-room hotel:

  • Complete renovation of the hotel rooms and their bathrooms
  • Corridors completely refurbished
  • Air conditioning installed

How it was done

One goal of the renovation was to keep disruption to the hotel's operations to a minimum, and the room renovation ran on a one-day takt in Mestamaster to achieve it. The corridor renovation and the air conditioning installation were managed in a more traditional way, planned around the work running in the takt areas. When the hotel closed temporarily during the coronavirus pandemic, the pace was accelerated from two rooms a day to three.

However, takt does require that the site organisation is fully committed to using this method. There is also a clear benefit to the client when there is transparent monitoring of the work.

Juha Haltia,

Project manager, Consti

Results

The project was completed on schedule and under budget. Consti named it worksite of the year, judged on financials, customer satisfaction and quality.