References
Built on real sites.
See how Finnish contractors use Mestamaster to deliver renovations faster — with less chaos and more predictability.
Book a free demoHotel Bonus Inn: 210 rooms renovated on a one-day takt
Hotel renovationConsti renovated the 210 rooms of Hotel Bonus Inn on a one-day takt time, with the goal of keeping disruption to the running hotel to a minimum. 100 takts covered 400 takt areas and 9,000 tasks in Mestamaster over 7 months. The project finished on schedule and under budget, and Consti named it worksite of the year.

Naistenklinikka: a maternity hospital renovated on a 2.5-day takt
Hospital renovationPeab renovated the patient wing of Naistenklinikka, part of HUS, on a 2.5-day takt. Mestamaster built the schedule, adjusted it as production ran, and trained the site foremen and the contractors. 96 takts ran across 54 takt areas over 12 months.

Kajavankatu: a pipe renovation in half the time, on a one-day takt
Pipe renovationRespect Project ran a pipe renovation through a 1970s concrete element apartment complex in Kerava on a one-day takt, with one apartment as the takt area. 130 takts ran across 95 apartments in 6 months, against the 12 months a conventional pipe renovation of this size takes.

Hyvinkää hospital: whole floors renovated on a 5- then 2.5-day takt
Heavy renovationLujatalo renovated whole floors of HUS Hyvinkää hospital on takt, across both phases of internal construction. The takt was five days during the early heavy work and 2.5 days in the later construction phase. Only demolition was left outside it. 63 takts ran across 40 takt areas over 29 months.

HEKA Laajasalo: 96 apartments renovated a month faster on a one-week takt
Housing renovationLujatalo renovated 96 Helsinki city rental apartments in Laajasalo on a one-week takt, with one floor as the takt area. 35 takts ran across 26 takt areas in nine months. The work inside the apartment houses finished a month ahead of the part of the project that ran without takt.

Hartela Oulu: a takt pilot that finished on time through Covid
New buildHartela built an elderly care rental building at Lintulammentie in Oulu, with business premises and shared spaces on the lower floors. The interior phase ran on a one-week takt, as Hartela's pilot with the method. 18 takts covered 14 takt areas and 79 apartments in 5 months, and the project finished on time.

Helsinki Opera House: renovated inside a summer break, finished weeks early
Heavy renovationSRG-Urakointi renovated parts of the Helsinki Opera House during the summer of 2023, with takt covering the HVAC upgrade, the sewer renewal and the 47 changing rooms. 27 takts ran across 15 takt areas in 3 months. SRG's share finished weeks ahead of schedule and under budget.

Henttaa Puistokatu: 119 new apartments and an interior phase that ran almost boring
New buildTencon built 119 rental apartments at Henttaa Puistokatu in Espoo, in a block with four staircases and underground parking. Mestamaster provided the scheduling app and the site support, with partner Tahcon running the daily support and the morning huddles. 76 takts ran across 38 takt areas in 9 months, to handover in early 2024.
Lujatalo: Lahti hospital handed over with zero defects
Hospital renovationLujatalo built temporary hospital facilities for the Päijät-Häme healthcare region on a one-week takt, with 600 tasks tracked in Mestamaster. The site ran 34 takts across 15 takt areas over eight months and handed the hospital over with zero defects.

Ready to see it on your projects?
Book a free 30-minute call - we will map your next project to a takt schedule and show you where Mestamaster would fit in.