Henttaa Puistokatu: 119 new apartments and an interior phase that ran almost boring

New buildTenconFinland

Tencon built 119 rental apartments at Henttaa Puistokatu in Espoo, in a block with four staircases and underground parking. Mestamaster provided the scheduling app and the site support, with partner Tahcon running the daily support and the morning huddles. 76 takts ran across 38 takt areas in 9 months, to handover in early 2024.

We were able to tighten the schedule and gain on lead time, particularly in how manoeuvrable and traceable the schedule became. Our interior phase manager says it would be hard to imagine doing a similar project without takt and Mestamaster.

Miika Puukka

Executive supervisor, Tencon

Tencon

119

apartments built on takt

In a block with four staircases.

15M€

Project total value

Apartments handed over in early 2024.

9

months duration

76

takts

38

takt areas

1,594

tasks in Mestamaster

The Customer

Tencon is part of the Avain Yhtiöt group and was founded in 2017 as a contractor specialising in new construction. It works in the Helsinki region on large apartment buildings, running projects as total contracts with the site and the procurement in its own hands.

What was done

A new block of apartment buildings in Espoo Henttaa:

  • A block with four staircases and underground parking
  • 119 rental apartments
  • Handed over in early 2024

How it was done

Tencon ran the project with Mestamaster and Tahcon. Mestamaster provided the scheduling app and the site support; Tahcon handled the daily support needs and the morning huddles. The site was supported with:

  • The schedule made together with site management
  • Meetings to bring the subcontractors in
  • Logistics designed and scheduled alongside the work
  • A review of the contracts
  • Updates and refinements to the takt schedule as production ran

Results

The gain on this project came from putting the logistics and the construction schedule together. The interior phase then ran stably, almost boringly so, which is what happens when the foresight and the production preparation have been done properly.