Helsinki Opera House: renovated inside a summer break, finished weeks early

Heavy renovationSRG-UrakointiFinland

SRG-Urakointi renovated parts of the Helsinki Opera House during the summer of 2023, with takt covering the HVAC upgrade, the sewer renewal and the 47 changing rooms. 27 takts ran across 15 takt areas in 3 months. SRG's share finished weeks ahead of schedule and under budget.

The schedule was given special attention here and everyone, including the subcontractors, followed it meticulously. In the areas with repetitive work, such as bathrooms, the work was completed well ahead of schedule.

Antti Alakoskela

Executive supervisor, SRG

SRG-Urakointi

Ahead

of schedule

SRG's share finished weeks early and under budget.

5.4M€

Takt's share

Of a 15M€ project: the HVAC, the sewers and the changing rooms.

3

months duration

Inside a summer break stretched to four months.

27

takts

On a three-day takt, two takts a week.

15

takt areas

333

tasks in Mestamaster

The Customer

SRG-Urakointi is a long-standing construction company with wide experience in renovation and new build. The building belongs to Senaatti, which owns and develops the cultural and historical properties of the Finnish state.

In the areas with repetitive work, such as bathrooms, the work was completed well ahead of schedule.

Antti Alakoskela,

Executive supervisor, SRG

What was done

The Opera House is 30 years old and parts of it were renovated over one summer. The wider job covered the main stage and the saunas as well; takt covered Mestamaster's share:

  • HVAC upgraded in the foyer
  • 6 km of sewage plumbing renewed
  • 47 changing rooms refurbished

How it was done

Senaatti wrote takt production into the procurement documents and pushed for it, so the takt was in place before the contractor started. The project opened with workshops on the schedule and moved into construction quickly. The contractor had seven working days a week available, so the takt was set at three days, two takts per week, which is not how a takt is usually divided. Mestamaster stayed on the project throughout and ran the morning huddles.

Results

The schedule was the constraint. The owner and the user needed the work finished inside a summer break stretched to four months, so that the Opera's autumn season could open in August. SRG's share was completed weeks ahead of schedule and under budget, and the repetitive parts of the work, the bathrooms among them, ran particularly well.