Lujatalo: Lahti hospital handed over with zero defects

Hospital renovationLujataloFinland

Lujatalo built temporary hospital facilities for the Päijät-Häme healthcare region on a one-week takt, with 600 tasks tracked in Mestamaster. The site ran 34 takts across 15 takt areas over eight months and handed the hospital over with zero defects.

We see a clear benefit of using takt as a way of making things more efficient, and this is also evident among contractors. The preparation and monitoring has been very successful co-operating with the contractors.

Jouni Orava

Executive Supervisor, Lujatalo

Lujatalo

0

defects at handover

The hospital was handed over with none

20M€

project size

Hospital works for the Päijät-Häme healthcare region

8

months duration

From the scheduling workshops to handover

34

takts

A one-week takt used throughout the site

15

takt areas

Each area with a named contractor and a fixed sequence

600

tasks in Mestamaster

The same schedule visible to every contractor

The Customer

Lujatalo is part of Luja Group, one of the largest groups in Finnish construction and an early adopter of digital methods on site. The end client, the Päijät-Häme healthcare region, organises services for more than 200,000 inhabitants across ten municipalities.

What was done

Temporary facilities built for a working hospital:

  • Various temporary hospital facilities built on the site
  • Technical building services organised and monitored from the early stages of the project
  • Scheduling and coordination run on a one-week takt across 15 takt areas

How it was done

The project had appointed foremen who already knew Mestamaster and takt scheduling, so under their lead the site carried more of the takt preparation than usual. Work started with the scheduling workshops and moved into a morning huddle routine that ran from there. The site used a one-week takt.

Results

The hospital work was scheduled so that a critical path to the start of the works was found, particularly in the early stages of the project. Schedule transparency improved and contractors had a clearer picture of what they owed in which space and at which time. The site kept up its task monitoring routine throughout, and the hospital was handed over with zero defects.