Kajavankatu: a pipe renovation in half the time, on a one-day takt

Pipe renovationRespect ProjectFinland

Respect Project ran a pipe renovation through a 1970s concrete element apartment complex in Kerava on a one-day takt, with one apartment as the takt area. 130 takts ran across 95 apartments in 6 months, against the 12 months a conventional pipe renovation of this size takes.

Takt showed how much good preparation matters. Design, resources and the preceding work all had to be finished on time. Meetings every morning kept everyone on the project up to date. It is a good method to focus on for production development.

Jarmo Mattsson

Supervisor, Respect Project

Respect Project

6

months

Half the duration of a conventional pipe renovation of this size

5–8

weeks per apartment

Down from the 10 weeks these renovations usually take

4M€

Project total value

A pipe renovation in Kerava, delivered in 6 months

95

renovated apartments

One apartment was one takt area, worked from the top of each line downwards

7,800

tasks

Tracked in Mestamaster across 130 takts

1

day takt

Takt length — the shortest takt Respect Project has run

The Customer

Respect Project has over ten years of experience in renovation projects and a revenue of around €17M. The building is a concrete element apartment complex from the 1970s.

The one-day takt certainly showed its sensitivity and its challenges, but it also proved what takt can do.

Jarmo Mattsson,

Supervisor, Respect Project

What was done

A pipe renovation of a 1970s concrete element apartment complex:

  • Sewer lines and fresh water piping renewed
  • Surfaces renovated across 95 apartments
  • Walls rebuilt where the old metal element bathrooms were removed

How it was done

The takt was one day, with one apartment as the takt area, and the work ran from the top of each line downwards. Almost everything inside the apartments was on takt, starting from the demolition. A one-day takt only holds if the routines around it hold: daily meetings, and subcontractors brought into the takt scheduling early, were what carried this project.

Results

Each apartment took 5 to 8 weeks instead of the usual 10, and the project finished in 6 months instead of 12. Respect Project went on to use takt on all of its projects, and extended it into project risk management.