Hyvinkää hospital: whole floors renovated on a 5- then 2.5-day takt

Heavy renovationLujataloFinland

Lujatalo renovated whole floors of HUS Hyvinkää hospital on takt, across both phases of internal construction. The takt was five days during the early heavy work and 2.5 days in the later construction phase. Only demolition was left outside it. 63 takts ran across 40 takt areas over 29 months.

Takt schedule was really helpful, it enabled more controlled working. Mestamaster app and their involvement helped in getting the process implemented and enabled the project flow really well.

Seppo Ung

Executive supervisor, Lujatalo

Lujatalo

34.2M€

Project total value

A 29-month heavy renovation for HUS, Finland's largest healthcare provider

29

months

Duration of the renovation across both phases

5

day takt

Phase I, during the early-phase heavy work

2.5

day takt

Phase II, in the later construction phase

63

takts

24 in phase I and 39 in phase II, across 12 + 28 takt areas

978

tasks

Tracked in Mestamaster — 334 in phase I, 644 in phase II

The Customer

Lujatalo is part of Luja Group, one of the biggest companies in the Finnish construction industry and a pioneer in using digital methods on site. The building belongs to HUS, the largest healthcare provider in Finland.

What was done

Takt covered the internal construction of the hospital, floor by floor:

  • Phases I and II of internal construction run on takt, whole floors at a time
  • Only demolition was left outside the takt
  • Scheduling workshops facilitated with the subcontractors, plus site management training

How it was done

Phase I used the five-day renovation takt as a learning experience of both takt production and Mestamaster. In phase II, Mestamaster facilitated the scheduling workshops with the subcontractors and trained site management — considerably less work than phase I, because the site already had the method behind it.

Results

The main benefits were excellent scheduling and building the different work phases in the right order. Takt time also enabled better risk control and resource efficiency.